Welcome to scot-rail.co.uk, Scotland's online railway community. The group is for any rail enthusiast interested in the railways and trains of Scotland. It not only consists of the wiki that you're reading now, but a busy online forum and mailing list, which was accessible to registered users. From April 2024 the forum has closed, with a replacement started on Groups.io.
Breadcrumb navigation
Planned Engineering Work during 2008.
A register of disruptive possessions is listed in Network Rail's Rules of the Route (Section 7) document.
ROTR 70sc08.pdf (471.11 Kb)
Below is a listing of daytime line blockages, and service alterations, for the period December 2007 - March 2008.
Saturday 8th - Sunday 9th December 2007
no major work
Sunday 16th December 2007
Main Worksites:
- Millerhill Yard: Track Renewal (Through Siding F7)
- Niddrie end of Milllerhill blocked. Any freight trains via Monktonhall Jn (with reverse at Drem if necessary).
Sunday 23rd - Monday 24th December 2007
Cross-Border Service Alterations:
- GNER trains start/terminate at Peterborough
Tuesday 25th December 2007 Christmas Day
Main Worksites:
- WCML 'Clyde Viaduct' (near Abington): Track renewal, Down line, 55m800y - 56m700y. (Mon 2230 to Thu 0640)
- No passenger trains running
Wednesday 26th December 2007 Boxing day
Main Worksites:
- Glasgow Central: Resignalling work (Tue 0035 to Thu 0500)
- Passenger service in SPT area only; 'Saturday service'.
- Glasgow Central (GLC) closed,
- Bus only: GLC - Whifflet, GLC - Paisley Canal, Shotts - Motherwell
- Bus: GLC - Crossmyloof (for East Kilbride/Kilmarnock trains)
- Bus: GLC - Pollokshields West (for Newton train)
- Bus: GLC - Pollokshields East (for Neilston trains)
- Bus: GLC - Paisley Gilmour Street (for Gourock, Wemyss Bay, Ardrossan, Largs and Ayr trains)
- FSR Christmas Service alterations
Main Worksites:
- Shields Junction: S&C renewals (Tue 0030 to Mon 7th Jan 0500)
- Bus: GLC - Paisley Gilmour Street (for Gourock, Wemyss Bay, Ardrossan, Largs and Ayr trains)
- No Access to Shields EMU Depot or Corkerhill DMU Depot.
- FSR Christmas Service alterations
Main Worksites:
- Edinburgh Waverley: OHLE works at West end (Mon 2330 to Sat 5th Jan 0430))
- Bay platforms 12,13,18 available from Thursday.
- Bay platforms 14,15,16,17, and lines X&Y through Mound tunnels blocked until 1st Jan.
- Edinburgh - Glasgow Queen Street: 1/2 hourly service.
- Haymarket/North Berwick trains start/terminate at Edinburgh Waverley.
- Fife Circle and Cowdenbeath trains start/terminate at Haymarket.
- NXEC and CrossCountry trains to/from Aberdeen/Inverness diverted via South Suburban line (do not call Haymarket).
- FSR Christmas Service alterations
Cross-Border Service Alterations:
- Virgin Trains: No trains to London Euston, start/terminate at Coventry
- Caledonian Sleepers: Diverted via ECML, reverse at Wembley for Euston.
Saturday 29th - Sunday 30th December 2007
Cross-Border Service Alterations:
- NXEC: Trains start/terminate at Newcastle (bus to Darlington)
Saturday 29th - Monday 31st December 2007
Cross-Border Service Alterations:
- Virgin Trains: No trains to London Euston, start/terminate at Coventry
- Caledonian Sleepers: Diverted via ECML, reverse at Wembley for Euston.
Saturday 29th - Monday 31st December 2007
Wednesday 2nd - Friday 4th January 2008
Main Worksites:
- Shields Junction: S&C renewals (Tue 25 Dec 0030 to Mon 7th Jan 0500)
- Bus: GLC - Paisley Gilmour Street (for Clyde Coast trains)
- No Access to Shields EMU Depot or Corkerhill DMU Depot.
- No Passenger service on 1st January
Main Worksites:
- Edinburgh Waverley: OHLE works at West end (Until Sat 5th Jan 0430)
- Bay platforms 14,15,16,17, and lines X&Y through Mound tunnels blocked
- Edinburgh - Glasgow Queen Street: 1/2 hourly service.
- Haymarket/North Berwick trains start/terminate at Edinburgh Waverley.
- Fife Circle and Cowdenbeath trains start/terminate at Haymarket.
- NXEC and CrossCountry trains to/from Aberdeen/Inverness diverted via South Suburban line (do not call Haymarket).
- 1st January: No First ScotRail trains, NXEC runnning South of Edinburgh only.
- FSR Christmas Service alterations
Wednesday 2nd January 2008
Main Worksites:
- Glasgow Central: Resignalling work (Tue 0035 to Thu 0500)
- Glasgow Central (GLC) closed,
- Bus only: GLC - Whifflet, GLC - Paisley Canal
- Bus: GLC - Crossmyloof (for East Kilbride/Kilmarnock trains)
- Bus: GLC - Pollokshields West (for Newton train)
- Bus: GLC - Pollokshields East (for Neilston trains)
- Bus: GLC - Paisley Gilmour Street (for Gourock, Wemyss Bay, Ardrossan, Largs and Ayr)
- FSR altered services Edinburgh - Shotts - Motherwell
- Virgin Trains and FTPE: start/terminate at Motherwell
- NXEC: Glasgow Central trains start/terminate at Edinburgh
- FSR Christmas Service alterations
Wednesday 2nd January 2008
Main Worksites:
- Larbert - Plean: Resignalling work
- Glasgow / Edinburgh - Aberdeen at 'Sunday service level'
- Glasgow - Aberdeen services diverted via Fife (Winchburgh - Dalmeny, Tay Bridge) non-stop to Dundee.
- 2-hourly Stirling - Perth - Dundee shuttle
- Hourly Glasgow - Falkirk Grahamston - Edinburgh serices
- Inverness trains via Fife
- FSR Christmas Service alterations
Saturday 5th - Sunday 6th January 2008
Cross-Border Service Alterations:
- NXEC and XC trains start/terminate at Newcastle (Bus to York or Darlington)
Main Worksites:
- Shields Junction: S&C renewals (until to Mon 7th Jan 0500)
- Bus: GLC - Paisley Gilmour Street (for Gourock, Wemyss Bay, Ardrossan, Largs and Ayr trains)
- No Access to Shields EMU Depot or Corkerhill DMU Depot.
- FSR Christmas Service alterations
Main Worksites:
- Cauldcotts (between Arbroath & Inverkeilot): Track Renewal (Down line, 21m 177y to 21m 1635y)
- Aberdeen - Glasgow/Edinburgh trains to start/terminate at Dundee.
- Bus: Aberdeen - Dundee
- Sleeper diverted to terminate/start at Perth (ECS to Inverness)
Main Worksites:
- Craigton (near Winchburgh): Rock cutting stabilisation.
- Glasgow Queen St - Falkirk High, Bus to Edinburgh
- Dunblane - Falkirk Grahamston, Bus to Edinburgh
- Extra trains: Edinburgh - Livingston South - Glasgow Central
- Inverness NXEC and 1M16 Sleeper via Forth Bridge.
- 1B01 Fort William - Edinburgh via Glasgow C. LL and Shotts
Sunday 6th January
Main Worksites:
- Annan - Gretna Junction: Redoubling works
- FSR trains Glasgow - Dumfries, Busses Dumfries - Carlisle
Saturday 12th - Sunday 13th January
Main Worksites:
- Kinnaber : Track Renewal (Up line, 203mi 952y to 205mi 302y)
- Aberdeen - Glasgow/Edinburgh trains to start/terminate at Dundee.
- Bus: Aberdeen - Dundee
- Sleeper diverted to terminate/start at Perth (ECS to Inverness)
Cross-Border Service Alterations:
- NXEC and XC trains start/terminate at Newcastle (Bus to York or Darlington)
Sunday 13th January
Main Worksites:
- Craigton (near Winchburgh): Rock cutting stabilisation.
- Glasgow Queen St - Falkirk High, Bus to Edinburgh
- Dunblane - Falkirk Grahamston, Bus to Edinburgh
- Extra trains: Edinburgh - Livingston South - Glasgow Central
- Inverness NXEC and 1M16 Sleeper via Forth Bridge.
- 1B01 Fort William - Edinburgh via Glasgow C. LL and Shotts
Main Worksites:
- Annan - Gretna Junction: Redoubling works
- FSR trains Glasgow - Dumfries, Busses Dumfries - Carlisle
Main Worksites:
- Shields Junction and GARL works
- Bus: Glasgow Central - Paisley Gilmour Street (for Gourock, Wemyss Bay, Ardrossan, Largs and Ayr trains)
- Glasgow - Kilmarnock - Ayr - Stranraer: altered service.
Saturday 19th - Sunday 20th January
Main Worksites:
- Kinnaber : Track Renewal (Up line, 203mi 952y to 205mi 302y)
- Aberdeen - Glasgow/Edinburgh trains to start/terminate at Dundee.
- Bus: Aberdeen - Dundee
- Sleeper diverted to terminate/start at Perth (ECS to Inverness)
Cross-Border Service Alterations:
- NXEC and XC trains start/terminate at Newcastle (Bus to York or Darlington)
Sunday 20th January
Main Worksites:
- Craigton (near Winchburgh): Rock cutting stabilisation.
- Glasgow Queen St - Falkirk High, Bus to Edinburgh
- Dunblane - Falkirk Grahamston, Bus to Edinburgh
- Extra trains: Edinburgh - Livingston South - Glasgow Central
- Inverness NXEC and 1M16 Sleeper via Forth Bridge.
- 1B01 Fort William - Edinburgh via Glasgow C. LL and Shotts
Main Worksites:
- Annan - Gretna Junction: Redoubling works
- FSR trains Glasgow - Dumfries, Busses Dumfries - Carlisle
Main Worksites:
- Shields Junction and GARL works
- Bus: Glasgow Central - Paisley Gilmour Street (for Gourock, Wemyss Bay, Ardrossan, Largs and Ayr trains)
- Glasgow - Kilmarnock - Ayr - Stranraer: altered service.
Saturday 26th - Sunday 27th January
Main Worksites:
- Glenury (north of Stonehaven): Track renewal (Down line 225mi 691y - 225mi 1053y)
- Aberdeen - Glasgow/Edinburgh trains to start/terminate at Dundee.
- Bus: Aberdeen - Dundee
- Sleeper diverted to terminate/start at Perth (ECS to Inverness)
Cross-Border Service Alterations:
- NXEC and XC trains start/terminate at Newcastle (Bus to York or Darlington)
Sunday 27th January - Friday 1st February
Main Worksites:
- Annan - Gretna Junction: Redoubling works
- FSR trains Glasgow - Dumfries, Busses Dumfries - Carlisle
Saturday 2nd - Sunday 3rd February
Main Worksites:
- Lockerbie to Carstairs South Jn: Blocked 06:00 Saturday to 05:30 Monday
- Evlanfoot: Track renewal, Up Line
- Virgin Trains 1M39 05:51 SO Glasgow C - Euston 57+390 via Kilmarnock
- All other Euston trains start/terminate at Carlisle, bus to Glasgow
- Some Birmingham trains start/terminate at Lockerbie, bus to Edinburgh/Glasgow
- First Transpennine Express: No trains operating north of Carlisle
- Caledonian Sleepers run ECML on Sunday night
Main Worksites:
- Slateford Junction: Switch and Crossing renewal Cancelled?
- No trains Edinburgh - Carstairs / Livingston South
- Sleepers diverted
Saturday 9th - Sunday 10th February
Main Worksites:
- Lockerbie to Carstairs South Jn: Blocked 06:00 Saturday to 05:30 Monday
- Evlanfoot: Track renewal, Up Line
- Beattock Summit: S&C renewal
- Virgin Trains 1M39 05:51 SO Glasgow C - Euston 57+390 via Kilmarnock
- All other Euston trains start/terminate at Carlisle, bus to Glasgow
- Some Birmingham trains start/terminate at Lockerbie, bus to Edinburgh/Glasgow
- First Transpennine Express: No trains operating north of Carlisle
- Caledonian Sleepers run ECML on Sunday night
Main Worksites:
- Carlisle - Grenta Jn: Blocked 22:30 Saturday to 14:30 Sunday
- Bus Carlisle - Dumfries
Sunday 10th February
Main Worksites:
- Arrochar: Track renewal
- 16:05 Mallaig - Crianlarich, 20:20 Crianlarich - Mallaig
- 18:11 Oban - Crianlarich, 20:14 Crianlarich - Oban
- replacement bus south of Crianlarich
- 1B01 Sleeper 19:00 Fort William - Edinburgh does run.
Saturday 16th - Sunday 17th February
Main Worksites:
- Lockerbie to Carstairs South Jn: Blocked 05:35 Saturday to 05:30 Monday
- Evlanfoot: Track renewal, Up Line
- Beattock Summit: S&C renewal
- Virgin Trains 1M39 05:51 SO Glasgow C - Euston 57+390 via Kilmarnock
- All other Euston trains start/terminate at Carlisle, bus to Glasgow
- Some Birmingham trains start/terminate at Lockerbie, bus to Edinburgh/Glasgow
- First Transpennine Express: No trains operating north of Carlisle
- Caledonian Sleepers run ECML on Sunday night
Sunday 17th February
Main Worksites:
- Arrochar: Track renewal
- 16:05 Mallaig - Crianlarich, 20:20 Crianlarich - Mallaig
- 18:11 Oban - Crianlarich, 20:14 Crianlarich - Oban
- replacement bus south of Crianlarich
- 1B01 Sleeper 19:00 Fort William - Edinburgh does run.
Main Worksites:
- Falkland (north of Markinch): Track renewal
- Ladybank: Signalling work
- NXEC to Aberdeen diverted via Stirling
- FSR Edinburgh - Aberdeen/Inverness diverted via Stirling
- Bus Kirkcaldy - Dundee
- XC trains not running north of Edinburgh
Saturday 23th - Sunday 24th February
Main Worksites:
- Lockerbie to Carstairs South Jn: Blocked 05:35 Saturday to 05:30 Monday
- Dalmakether: Track renewal, Up Line
- Beattock Summit: S&C renewal
- Virgin Trains 1M39 05:51 SO Glasgow C - Euston 57+390 via Kilmarnock
- All other Euston trains start/terminate at Carlisle, bus to Glasgow
- Some Birmingham trains start/terminate at Lockerbie, bus to Edinburgh/Glasgow
- First Transpennine Express: No trains operating north of Carlisle
- Caledonian Sleepers run ECML on Sunday night
Sunday 24th February
Main Worksites:
- Arrochar: Track renewal
- 16:05 Mallaig - Crianlarich, 20:20 Crianlarich - Mallaig
- 18:11 Oban - Crianlarich, 20:14 Crianlarich - Oban
- replacement bus south of Crianlarich
- 1B01 Sleeper 19:00 Fort William - Edinburgh does run.
Main Worksites:
- Falkland (north of Markinch): Track renewal
- NXEC to Aberdeen diverted via Stirling
- FSR Edinburgh - Aberdeen/Inverness diverted via Stirling
- Bus Kirkcaldy - Dundee
- XC trains not running north of Edinburgh
Main Worksites:
- Shields Junction (S&C Tamping) and OHLE works
- Bus: Glasgow Central - Paisley Gilmour Street (for Gourock, Wemyss Bay, Ardrossan, Largs and Ayr trains)
- Glasgow - Kilmarnock - Ayr - Stranraer: altered service.
Saturday 1st - Sunday 2nd March
Main Worksites:
- Lockerbie to Carstairs South Jn: Blocked 05:30 Saturday to 05:30 Monday
- Dalmkether: Track renewal, Up Line (33m0y - 33m1748y)
- Virgin Trains 1M39 05:51 SO Glasgow C - Euston 57+390 via Kilmarnock
- All other Euston trains start/terminate at Carlisle, bus to Glasgow
- Some Birmingham trains start/terminate at Lockerbie, bus to Edinburgh/Glasgow
- First Transpennine Express: No trains operating north of Carlisle
- Caledonian Sleepers run ECML on Sunday night
Cross-Border Service Alterations:
- NXEC trains diverted York - Leeds - Doncaster
Sunday 2nd March
Main Worksites:
- Gorton: Track renewal (58m1627y - 59m609y)
- Replacement bus Crianlarich - Fort William (connects with Oban train)
- 16:05 Mallaig - Tulloch, 21:35 Tulloch - Mallaig
- 1B01 Sleeper 19:00 Fort William - Edinburgh does run.
Main Worksites:
- Falkland (north of Markinch): Track renewal follow-up work
- NXEC to Aberdeen diverted via Stirling
- FSR Edinburgh - Aberdeen/Inverness diverted via Stirling
- Bus Kirkcaldy - Dundee
- XC trains not running north of Edinburgh
Main Worksites:
- Shields Junction (S&C Tamping) and OHLE works
- Bus: Glasgow Central - Paisley Gilmour Street (for Gourock, Wemyss Bay, Ardrossan, Largs and Ayr trains)
- Glasgow - Kilmarnock - Ayr - Stranraer: altered service.
Saturday 8th - Sunday 9th March
Main Worksites:
- Lockerbie to Carstairs South Jn: Blocked 05:30 Saturday to 05:30 Monday
- Wamphhray: Track renewal, Dn Line (34m838y - 35m830y)
- Abington South: Track renewal, Dn Line (53m1193y - 54m1540y)
- Virgin Trains 1M39 05:51 SO Glasgow C - Euston 57+390 via Kilmarnock
- All other Euston trains start/terminate at Carlisle, bus to Glasgow
- Some Birmingham trains start/terminate at Lockerbie, bus to Edinburgh/Glasgow
- First Transpennine Express: No trains operating north of Carlisle
- Caledonian Sleepers run ECML on Sunday night
Main Worksites:
- Carlisle - Grenta Jn: Blocked 22:30 Saturday to 14:30 Sunday
- Bus Carlisle - Dumfries
Cross-Border Service Alterations:
- NXEC trains diverted York - Leeds - Doncaster
Sunday 9th March
Main Worksites:
- Soldiers Trench (South of Rannoch): Track renewal (60m1409y - 61m839y)
- Replacement bus Crianlarich - Fort William (connects with Oban train)
- 16:05 Mallaig - Tulloch, 21:35 Tulloch - Mallaig
- 1B01 Sleeper 19:00 Fort William - Edinburgh does run.
Saturday 15th - Sunday 16th March
Main Worksites:
- Lockerbie to Carstairs South Jn: Blocked 05:30 Saturday to 05:30 Monday
- Auchencastle: Track renewal, Up Line (41m90y - 41m1563y)
- Virgin Trains 1M39 05:51 SO Glasgow C - Euston 57+390 via Kilmarnock
- All other Euston trains start/terminate at Carlisle, bus to Glasgow
- Some Birmingham trains start/terminate at Lockerbie, bus to Edinburgh/Glasgow
- First Transpennine Express: No trains operating north of Carlisle
- Caledonian Sleepers run ECML on Sunday night
Main Worksites:
- Carlisle - Grenta Jn: Blocked 22:30 Saturday to 14:30 Sunday
- Bus Carlisle - Dumfries
Cross-Border Service Alterations:
- NXEC trains diverted York - Leeds - Doncaster
Sunday 16th March
Main Worksites:
- Gorton: Track renewal
- Replacement bus Crianlarich - Fort William (connects with Oban train)
- 16:05 Mallaig - Tulloch, 21:35 Tulloch - Mallaig
- 1B01 Sleeper 19:00 Fort William - Edinburgh does run.
Main Worksites:
- Larbert - Stirling: Signalling work
- Glasgow - Aberdeen services diverted via Fife (Winchburgh - Dalmeny, Tay Bridge) non-stop to Dundee.
- Glasgow - Stirling diverted to Falkirk Grahamston
- Edinburgh - Falkirk Grahmston, Bus to/from Dunblane
- Glasgow - Inverness trains via Fife.
- NXEC Highland Chieftain via Fife.
Saturday 22nd - Sunday 23rd March Easter Day
Main Worksites:
- Zone boundary to Carstairs South Jn: Blocked 21:10 Saturday to 11:40 Sunday
Cross-Border Service Alterations:
- NXEC trains diverted York - Leeds - Doncaster
- First Transpennine Express: No trains operating north of Carlisle
Saturday 22nd - Monday 24th March
Main Worksites:
- Stirling - Alloa - Kincardine: Signal commissioning
- Larbert: Track renewal, Down Line (109m1612y - 110m498y)
- Glasgow - Aberdeen services diverted via Fife (Winchburgh - Dalmeny, Tay Bridge) non-stop to Dundee.
- Glasgow - Stirling / Dunblane diverted to Falkirk Grahamston and through to Edinburgh (Sat/Mon)
- Glasgow - Stirling diverted to Falkirk Grahamston (Sunday)
- Newcraighall/Edinburgh - Falkirk Grahmston, Bus to/from Dunblane
- Glasgow - Inverness trains via Fife.
- NXEC Highland Chieftain via Fife.
Cross-Border Service Alterations:
- No Virgin Trains services to London Euston - all terminate Birmingham/Coventry
- Caledonian Sleepers run ECML on Sunday and Monday nights
Sunday 23rd March Easter Day
Main Worksites:
- Glengarnock: Re-railing (19m880y - 21m10y)
- Glasgow Central - Johnstone, bus to Irvine (am) / Killwinning (pm)
- Ayr - Largs (via Byrehill Jn - Dubbs Jn) until 12.43
- Kilwinning - Ayr / Largs (pm)
- Glasgow Central - Kilmarnock - Ayr - Stranraer amended service
Cross-Border Service Alterations:
- Busses replace trains Carlisle - Preston on Easter Sunday.
Saturday 29th - Sunday 30th March
Cross-Border Service Alterations:
- FTPX: Edinburgh (Sunday) and Glasgow to/from Carlisle only
- Virgin Trains: Some diverted via S&C route
Saturday 29th - Friday 4th April
Main Worksites:
- Various sites from Locheilside to Mallaig
- Busses replace trains between Mallaig and Fort William.
- Line reopens Monday 14th April
Saturday 29th
Main Worksites:
- Ampherlaw: Track Renewal (Down line, 77m2y - 92m452y)
- Kaimes: Track Renewal (Down line, 92m1000y - 92m1479y)
- FSR: Edinburgh - Shotts - Glasgow: bus replaces train between Edinburgh and Livingston South
- NXEC: bus replaces train between Edinburgh and Glasgow Central
- Virgin Trains: bus replaces train between Edinburgh and Lockerbie
Sunday 30th March
Main Worksites:
- Lochwinnoch: Track renewal, Up line (17m550y - 16m1095y)
- Glasgow Central - Johnstone, bus to Killwinning
- Kilwinning - Ayr / Largs
- Glasgow Central - Kilmarnock - Ayr - Stranraer amended service
- EWS Hunterstone - Longannet "withdrawn" (ROTR)
Main Worksites:
- Annan - Gretna Junction: Redoubling works
- FSR trains Glasgow - Dumfries, Busses Dumfries - Carlisle
Saturday 5th - Sunday 6th April
Cross-Border Service Alterations:
- FTPX: Edinburgh (Sunday) and Glasgow to/from Carlisle only
- Virgin Trains: Some diverted via S&C route
Saturday 5th - Friday 11th April
Main Worksites:
- Various sites from Locheilside to Mallaig
- Busses replace trains between Mallaig and Fort William.
- Line reopens Monday 14th April
Saturday 5th
Main Worksites:
- Ampherlaw: Track Renewal (Down line, 77m452y - 77m900y)
- Kaimes: Track Renewal (Down line, 92m1479y - 92m1759y)
- FSR: Edinburgh - Shotts - Glasgow: bus replaces train between Edinburgh and Livingston South
- NXEC: bus replaces train between Edinburgh and Glasgow Central
- Virgin Trains: bus replaces train between Edinburgh and Lockerbie
Sunday 6th April
Main Worksites:
- Lochwinnoch: Track renewal, Up line (17m550y - 15m1638y)
- Glasgow Central - Johnstone, bus to Killwinning
- Kilwinning - Ayr / Largs
- Glasgow Central - Kilmarnock - Ayr - Stranraer amended service
- EWS Hunterstone - Longannet "withdrawn" (ROTR)
Main Worksites:
- Annan - Gretna Junction: Redoubling works
- FSR trains Glasgow - Dumfries, Busses Dumfries - Carlisle
Main Worksites:
- Carmuirs West: S&C tamping
- Glasgow - Stirling/Aberdeen trains reverse Polmont until 12.30pm
Main Worksites:
- Stirling: Track renewal, through platforms 6 and 9
- None.
Saturday 12th - Sunday 13th April
Cross-Border Service Alterations:
- FTPX: Edinburgh (Sunday) and Glasgow to/from Carlisle only
- Virgin Trains: Some diverted via S&C route
Main Worksites:
- Various sites from Locheilside to Mallaig
- Busses replace trains between Mallaig and Fort William.
- Line reopens Monday 14th April.
Saturday 5th
Main Worksites:
- Kirknewton/Kaimes: Drainage work. Curriehill: OLHE work
- FSR: Edinburgh - Shotts - Glasgow: bus replaces train between Edinburgh and Livingston South
- NXEC: bus replaces train between Edinburgh and Glasgow Central
- Virgin Trains: bus replaces train between Edinburgh and Lockerbie
Sunday 6th April
Main Worksites:
- Lochwinnoch/Beith: Track renewal, Up line (17m550y - 15m1638y)
- Glasgow Central - Johnstone, bus to Killwinning
- Kilwinning - Ayr / Largs
- Glasgow Central - Kilmarnock - Ayr - Stranraer amended service
- EWS Hunterstone - Longannet "withdrawn" (ROTR)
Main Worksites:
- Annan - Gretna Junction: Redoubling works
- FSR trains Glasgow - Dumfries, Busses Dumfries - Carlisle
Main Worksites:
- Stirling: Track renewal, through platforms 6 and 9
- None.
External Links:
- First ScotRail: Journey Check
- NXEC: Amended timetables
- Virgin Trains: Engineering Works
- CrossCountry: Travel Updates
- FTPE: Engineering Works
- National Rail: Planned Engineering Works
- Network Rail: Operational Rules (ROTP)
- ROTP: register of possessions 2008 (2mb PDF)
- ROTP: register of possessions 2009 (2mb PDF)